49MW energy storage approval quashed after council accepts EIA error

The High Court has quashed a planning approval granted for two energy storage systems on a rural site in Hampshire after the local council accepted it had erred in concluding that the project was not development that required an environmental impact assessment

High Court
High Court: has quashed energy storage approval

The High Court has quashed a planning approval granted for two energy storage systems on a rural site in Hampshire after the local council accepted it had erred in concluding that the project was not development that required an environmental impact assessment (EIA).